Finland halts Google data centre work — 300 hectares of forest cut before the review
On October 6, 2026, Finland's Licensing and Supervision Agency (LVV) ordered Tuike Finland, Google's local subsidiary, to stop heavy site work at two planned data centres in Muhos and Kajaani immediately and no later than October 23. The reason: tree felling, topsoil removal and road building went ahead before the legally required environmental impact assessments were finished, and about 300 hectares of forest were reportedly lost at Muhos alone. The halt lasts until both assessments are complete; only easily reversible work such as surveys and soil tests may continue. The two sites are part of the €13 billion (about $15 billion) Finland investment Google announced in September. Google said it 'fell short of' its own standards and will follow the agency's direction
The three lines
- Order — LVV, Oct 6: stop heavy work at Muhos and Kajaani by Oct 23 at the latest, until EIAs finish
- Why — forest cleared and topsoil stripped before assessments; ~300 ha lost at Muhos alone
- Stakes — part of Google's €13B Finland plan; Google admits it 'fell short', will replant 130 ha
Key questions
- Why did Finland halt Google data centers
- **Work started before environmental impact assessments (EIAs) were done.** | Item | Detail | |---|---| | Authority | Licensing and Supervision Agency (LVV) | | Target | Tuike Finland Oy (Google subsidiary) | | Sites | Muhos, Kajaani | | Order date | Oct 6, 2026 | | Deadline | Immediately, no later than Oct 23 | | Lifted when | Both EIAs are complete |
- Google Finland investment 13 billion euros
- **€13 billion, Google's largest single investment in Europe.** | Site | Plan | |---|---| | Hamina | Expansion of existing data centre | | Muhos | New data centre (halted) | | Kajaani | New data centre (halted) | | Vaala | New data centre | | Announced | Sept 9, 2026 |
- What work is allowed during Finland's Google halt
- **Only light, reversible work.** | Stopped | Still allowed | |---|---| | Tree felling, topsoil removal | Planning and design | | Digging, blasting, crushing | Measurements | | Moving soil, ditching | Soil surveys | | Site roads, storage areas | Other minor, reversible work |
In the AI data-centre race, the scarcest resource is turning out to be neither chips nor power but permission. On October 6, 2026, Finland's Licensing and Supervision Agency (LVV) ordered Tuike Finland, Google's Finnish subsidiary, to stop site work at two data centres under development in Muhos and Kajaani in the country's north. The problem: forest was cut and ground dug before the required environmental impact assessments (EIAs) were finished. The sites are central to the €13 billion plan Google announced in September as its largest single investment in Europe.
1. The order: what stops and what continues
| Item | Detail |
|---|---|
| Order date | Oct 6, 2026 |
| Stop deadline | Immediately, no later than Oct 23 |
| Written response | Tuike Finland must explain itself by Oct 14 |
| Duration | Until EIA procedures for both projects are complete |
| If ignored | Enforcement including a conditional fine (amount not set) |
| Stopped | Still allowed |
|---|---|
| Tree felling, topsoil removal | Planning |
| Digging, blasting, quarrying, crushing | Measurements |
| Moving soil, ditching, culvert changes | Soil surveys |
| Site roads, storage areas, stormwater works | Minor, easily reversible work |
Tommi Muilu, head of the LVV's environment department, said the work done so far changes the environment and has exactly the impacts an EIA is meant to assess. If the land is transformed before the assessment concludes, the assessment loses its point.
2. How much was cleared: 300 hectares, or more
| Source | Area cleared |
|---|---|
| Public information cited by LVV (Sept 18) | About 300 ha at Muhos |
| ForkLog | ~330 ha at Muhos + ~200 ha at Kajaani = over 500 ha |
| Finnish Association for Nature Conservation | About 420 football pitches (satellite estimate) |
Three hundred hectares is 3 square kilometres, roughly the size of Seoul's Yeouido island or about 560 American football fields. Hanna Halmeenpää, chair of the Finnish Association for Nature Conservation, said loggers cut nature sites that should have been preserved and asked authorities to halt the work. The sites were already legally tangled: local plans in both towns face administrative court appeals, so a building ban applies and tree felling needs separate permission. Google maintained the felling complied with the Forestry Act.
3. Google's response and the stakes
| Site | Plan |
|---|---|
| Hamina | Expansion of existing data centre |
| Muhos | New (halted) |
| Kajaani | New (halted) |
| Vaala | New |
| Total | €13 billion, announced Sept 9, 2026 |
Google spokesperson Sondre Ronander said the company "fell short of" its own high standards at the site, while saying it acted in good faith under the Forestry Act, ran nature surveys and protected high-value areas. Google will follow the LVV's guidance and plant trees across 130 hectares at Muhos.
Environment and Climate Minister Sari Multala said she expects the projects to slip and called it "a serious matter" if the company and its subcontractors acted as alleged. A citizens' initiative calling for stricter rules on data centres' energy and environmental impact gathered more than 50,000 signatures in three days, enough for parliament to consider it. From 2027, the EU will rate data centres on energy and water use.
4. What remains unclear
- Assessment timeline: when the two EIAs will finish hasn't been disclosed, and work stays halted until then.
- Kajaani's cleared area: the ~200 hectares comes from a single outlet.
- Penalties: no fine has been imposed; Tuike's written response on Oct 14 is the next milestone.
- Delay to operations: Google framed the investment over 2027–2028; how far Muhos and Kajaani slip is unknown.
- Related: how AI data centres secure power is covered in "Google–Constellation 3.6 GW power deal."
Sources
- The Next Web — Finland orders Google to stop clearing forest at two data centre sites
- CGTN — Finland halts Google data center work over environmental assessment
- NordiskPost — Finland tells Google to halt data centre work in Muhos and Kajaani
- ForkLog — Finland Halts Google Data Center Projects After 500 Hectares of Forest Cleared
- Courthouse News — Finland orders halt to work on Google's data center sites