800V DC data center — China's Ulanqab campus goes live, cutting out the transformer, UPS and rectifier stages
An 800V DC data center sends power to server racks as 800-volt direct current instead of converting grid AC several times along the way. China's Envision Group said on November 2, 2026, that such a system is running live AI workloads at its Galaxy campus in Ulanqab, Inner Mongolia, calling it a world first. Solid-state transformers convert 10 kV grid AC directly to an 800V DC bus, eliminating the low-voltage transformer, UPS and rectifier stages. SemiAnalysis, which visited the site, says the campus is planned for up to 800 MW of IT capacity, with the first 120 MW built within a year at about a fifth of US costs.
The three lines
- How — solid-state transformers turn 10 kV AC straight into 800V DC, removing three conversion stages
- Where — Envision's Galaxy campus, Ulanqab; up to 800 MW planned, first 120 MW delivered in August
- Why now — AI racks now draw hundreds of kilowatts, straining low-voltage distribution
Key questions
- what is an 800v dc data center
- **A power design that delivers 800-volt direct current to the racks, cutting conversion steps to save energy and space.** | Stage | Conventional AC | Envision 800V DC | |---|---|---| | Grid input | Medium-voltage AC | 10 kV AC | | Low-voltage transformer | Yes | No (solid-state transformer) | | UPS | Yes | No (integrated battery storage) | | Rectifier | Yes | No | | Rack input | AC or low-voltage DC | 800V DC bus |
- ulanqab data center envision
- **Envision's Galaxy campus in Ulanqab, Inner Mongolia, built to suit two Chinese internet giants (SemiAnalysis).** | Item | Detail | |---|---| | Operator | Envision Group | | Planned capacity | Up to 800 MW IT, four phases | | Phase 1 | 120 MW, delivered August 2026, built within a year | | Full build-out | End of 2027 target | | Power | Mostly own wind farms plus 4-hour batteries | | Cost | About a fifth of US costs; under $3 million per MW |
- what is a solid state transformer
- **A transformer that uses power semiconductors instead of copper coils and iron cores, and can output DC directly.** | | Conventional transformer | Solid-state transformer | |---|---|---| | Principle | Electromagnetic induction | High-speed semiconductor switching | | Output | AC | AC or DC | | Size | Large, heavy | Compact | | Efficiency | — | Reported above 98.5%; no official single figure |
An 800V DC data center delivers electricity to servers without changing trains along the way. Conventional facilities step grid AC down through transformers, pass it through uninterruptible power supplies and convert it to DC with rectifiers, losing a little energy and floor space at each stage. The 800V DC approach removes those middle steps.
On November 2, 2026, China's Envision Group said an integrated 800V DC system is running live AI workloads at its Galaxy campus in Ulanqab, Inner Mongolia, calling it a world first. SemiAnalysis, which toured the site, called it "China's Stargate."
1. How it works
The key device is the solid-state transformer (SST), which uses power semiconductors rather than coils and iron. It takes 10 kV grid AC and outputs an 800V DC bus directly, combined with battery storage and DC-DC converters for the IT load.
| Stage | Conventional AC | Envision 800V DC |
|---|---|---|
| Low-voltage transformer | Required | Removed |
| UPS | Required | Removed (battery integrated) |
| Rectifier | Required | Removed |
| Substation build time | About 6 months | Under 3 months (prefabricated) |
Why now: AI racks have grown from tens to hundreds of kilowatts — an Nvidia Vera Rubin rack is in the 250 kW class. Delivering that at low voltage means huge currents and thick copper; raising the voltage cuts both. Nvidia has also signaled plans for 800V DC in future racks.
2. The Galaxy campus
| Item | Galaxy, Ulanqab (Envision) | Stargate Abilene (Crusoe, Oracle, OpenAI) |
|---|---|---|
| Planned size | Up to 800 MW IT, four phases | 1.2 GW power, about 820 MW IT |
| First phase | 120 MW within a year (Aug 2026) | Construction began mid-2024 |
| Main power | Own wind plus 4-hour batteries | Grid plus on-site gas turbines |
| Cost | About a fifth of US; under $3M per MW | — |
Envision's own wind farms total 420 MW, about 1.75 times the 240 MW load, linked by a dedicated line; it aims to supply over 60% of the first two phases from them. Liquid- and air-cooled servers share one water loop with no central chiller. Power costs about $0.055 per kWh all-in, and Chinese data center rents have roughly halved in five years to about $40 per kW per month.
3. What's still unclear
| Issue | Known | Unknown |
|---|---|---|
| 800V DC in service | Live AI workloads; 5 MW pilot hall | Total size in service |
| Efficiency | Reported above 98.5% | Official figure |
| Campus scale | Up to 800 MW (SemiAnalysis) | Link to a reported 3 GW area plan |
| Chips | — | Which AI accelerators |
The contrast is clear even if DC distribution's future is not: while US AI labs buy gas generators to avoid grid queues — see our report on Anthropic's $3.4 billion generator deal — China is building comparable campuses faster and cheaper with wind and DC power. Our explainer on behind-the-meter power covers the US approach.
Sources
- SemiAnalysis — We visited China's Stargate in Inner Mongolia (2026-11)
- DatacenterDynamics — Envision claims to be running the world's first 800VDC data center in Ulanqab, China (2026-11)
- Tom's Hardware — China deploys world's first 800-volt DC power system for massive AI data center (2026-11)
- pv magazine — Envision claims world first with 800 V DC architecture for AI data center (2026-11-02)